CLIENT: Johansen Construction Company
PROJECT OWNER: City of Sammamish
START DATE: 11/2019
END DATE: 07/2021
ROLE: Subcontractor
MAJOR WORK ELEMENTS:
- 720 LF of 8 FT & 10 FT Dia. drilled shafts supporting bridge structure through sensitive wetland area to be reclaimed as part of project
- 2,755 LF of Prestressed Concrete Girders placed at night over the course of several shifts
- Over 1,500 LF of various CIP Barriers, including a challenging design that includes a window through barrier for visibility to other side
- Two multi-lane roundabouts involving stamped and colored concrete finishes constructed in a staged approach to accommodate traffic control
- Concrete stairway and ADA Ramp built to provide middle school students access to adjacent school
Project Photos
Project type
Structures