BOUNDARY BRIDGE - REMOVE FISH BARRIER PROJECT
CLIENT: WHH Nisqually Federal Services
PROJECT OWNER: Washington State Department Of Transportation (WSDOT)
START DATE: 05/2019
END DATE: 08/2021
ROLE: Subcontractor
MAJOR WORK ELEMENTS:
- Remote project location which dictated short construction seasons
- Staged bridge construction which required 1/2 of bridge to be constructed at a time to allow for shifting of traffic onto partially completed bridge
- 165 CY of Class 4000 Concrete to support single span prestressed concrete girder bridge
- Placement of 11 CY of Ultra High Performance Concrete (UHPC) which was required to reach 10k PSI within 7 days. New concrete technology designed by WSDOT and placed between girders to allow for 2 staged bridge construction.
- 588 LF of prestressed concrete girders