CLIENT: City of Woodinville
PROJECT OWNER: City of Woodinville
START DATE: 04/2018
END DATE: 10/2019
ROLE: Prime Contractor
MAJOR WORK ELEMENTS:
- Retrofit of an existing Prestressed Girder bridge over Sammamish River to add Pedestrian sidewalk
- Construction of a new Prestressed Girder single span bridge over Sammamish River completed within one foot of existing adjacent bridge on one side and active railroad track on the other.
- Challenging Traffic Control constraints maintained throughout construction
- 240 LF of 4 FT. Diameter Bridge Shafts
- Installation of 690 LF of WF58G Prestressed Concrete Girders over the Sammamish River and an active Bike/Pedestrian Trail
- Installation of two new Rail Road Crossings
- Placement of 150 CY of Concrete Class 4000 for Bridge
Project Photos
Project type
Structures